Why is prioritisation more valuable than estimation in early planning?
- A Knowing what matters most enables value delivery even when estimates prove wrong
- B Estimation is impossible
- C Prioritisation is faster
- D Estimates are never required
Answer
Knowing what matters most enables value delivery even when estimates prove wrong
Estimates are uncertain early, but sequencing by value means the most important work is delivered regardless of how the schedule shifts.