What is scope creep?

  1. A Uncontrolled expansion of scope without corresponding adjustment to time, cost or resources
  2. B Any change to requirements
  3. C Reducing project scope
  4. D Adding team members
Answer

Uncontrolled expansion of scope without corresponding adjustment to time, cost or resources

Change itself is normal. The problem is change absorbed silently without renegotiating the constraints.