What is scope creep?
- A Uncontrolled expansion of scope without corresponding adjustment to time, cost or resources
- B Any change to requirements
- C Reducing project scope
- D Adding team members
Answer
Uncontrolled expansion of scope without corresponding adjustment to time, cost or resources
Change itself is normal. The problem is change absorbed silently without renegotiating the constraints.