What is the purpose of a change control process?

  1. A Assessing the impact of a proposed change and obtaining a decision before it is implemented
  2. B Preventing all changes
  3. C Documenting completed work
  4. D Assigning blame for delays
Answer

Assessing the impact of a proposed change and obtaining a decision before it is implemented

Impact assessment across cost, schedule, risk and dependencies is what turns a request into an informed decision.